Development Update - Feb 2025

"The development at Hobbs Bay Estate is progressing well. Road kerbing is nearly complete within the first stage, and we have received approval to remove exotic trees from the esplanade reserve, allowing for the planting of native species to enhance the area and stabilize the coastal cliff.
All wastewater lines are installed, with only the main connection to the existing Watercare pump station remaining. The stormwater system is operational, and a permanent stormwater treatment pond is under construction. Utility services, including power and fibre, are being installed and are on track for completion in the coming weeks.
Our civil contractor has allocated additional resources to ensure the project is completed to a high standard and on schedule." - Ettiene Petzer, Project Manager